Quiz: Software Project Management(B)(SS ZG622)

1. The waterfall model of software development is
Select one:
a. The best approach to use for projects with large development teams
b. A good approach when a working program is required quickly
c. A reasonable approach when requirements are well defined
d. An old fashioned model that is not used any more
Answer: C
2. Which of the following is not a main project objective?
Select one:
a. Cost
b. Structure
c. Time
d. Quality
Answer: B
3. LOC-based estimation techniques require problem decomposition based on
Select one:
a. software functions
b. project schedule
c. process activities
d. information domain values
Answer: A
4. From among the following activities, which is the best example of a project?
Select one:
a. Developing HIV vaccine
b. Processing insurance claims
c. Writing a term paper
d. Producing automobiles
Answer:
5. The objective of software project planning is to
Select one:
a. determine the probable profit margin prior to bidding on a project
b. make use of historical project data
c. convince the customer that a project is feasible
d. enable a manager to make reasonable estimates of cost and schedule
Answer: D
6. Which of these are the 5 generic software engineering framework activities?
Select one:
a. communication, risk management, measurement, production, reviewing
b. communication, planning, modeling, construction, deployment
c. analysis, designing, programming, debugging, maintenance
d. analysis, planning, designing, programming, testing
Answer: B
7. "To construct a high-quality, custom home within eight months at costs not to exceed twenty lakh rupees" is best classified as
Select one:
a. A limit
b. A deliverable
c. An objective
d. A milestone
Answer: C
8. Which these are reasons for using technical product measures during software development?
Select one:
a. they help capturing client requirements clearly
b. they allow all quality software quality information to be expressed unambiguously as a single number
c. provide software engineers with an objective mechanism for assessing software quality
d. large body of scientific evidence supports their use
Answer: C
9. Architectural design metrics focus on
Select one:
a. Program Structure
b. Module complexity
c. Data relationships
d. Effectiveness of modularization
Answer: D
10. Which of the following is not a main element of the project management process?
Select one:
a. Estimate
b. Monitor
c. Schedule
d. Design
Answer: D
11. The process of forecasting or approximating the time and cost of completing project deliverables is called
Select one:
a. Budgeting
b. Estimating
c. Planning
d. Accounting
Answer: B
12. The incremental model of software development is
Select one:
a. A revolutionary model that is not used for commercial products
b. A reasonable approach when requirements are well defined
c. A good approach when a working core product is required quickly
d. The best approach to use for projects with large development teams
Answer: C
13. Learning curves are more likely to apply in situations where most of the costs are
Select one:
a. Materials
b. Overhead
c. Prototype
d. Labor
Answer: D
14. Which of the following is not necessary to apply agility to a software process?
Select one:
a. Eliminate the use of project planning and testing
b. Process allows team to streamline tasks
c. Uses incremental product delivery strategy
d. Only essential work products are produced
Answer: A
15. Software feasibility is based on which of the following
Select one:
a. business and marketing concerns
b. technical prowess of the developers
c. technology, finance, time, resources
d. scope and market
Answer: C
16. Identify from the below who is NOT a typical project stakeholder?
Select one:
a. End-user of the project
b. Project Manager
c. Shareholder of the vendor organization
d. CFO of the client organization
Answer: C
17. The tendency for the project deliverables to expand over time-usually by changing requirements, specifications, and priorities-is called
Select one:
a. Project add-on
b. Scope enhancement
c. Scope creep
d. Project bloat
Answer: C
18. Which of the following is not one of the commonly heard comments of project managers?
Select one:
a. Why is this project so strongly linked to the strategic plan?
b. Why are we doing this project?
c. Where did this project come from?
d. Where are we going to get the resources to do this project?
Answer: A
19. The highest element in the hierarchical breakdown of the WBS is
Select one:
a. Project
b. Major deliverable
c. A work package
d. Framework activity
Answer: A
20. Which of the following is especially useful for monitoring project progress against plan?
Select one:
a. Gantt Charts
b. Flow diagrams
c. Sequence Diagrams
d. Network diagrams
Answer: A

3 comments:

  1. The starting place for exploring business management & leadership; helping new managers get started and experienced managers get better popular project management software

    ReplyDelete
    Replies

    1. IEEE Final Year projects Project Center in Chennai are consistently sought after. Final Year Students Projects take a shot at them to improve their aptitudes, while specialists like the enjoyment in interfering with innovation. For experts, it's an alternate ball game through and through. Smaller than expected IEEE Final Year project centers ground for all fragments of CSE & IT engineers hoping to assemble. <Final Year Projects for CSE It gives you tips and rules that is progressively critical to consider while choosing any final year project point.

      JavaScript Training in Chennai

      JavaScript Training in Chennai

      The Angular Training covers a wide range of topics including Components, project projects for cseAngular Directives, Angular Services, Pipes, security fundamentals, Routing, and Angular programmability. The new Angular TRaining will lay the foundation you need to specialise in Single Page Application developer. Angular Training

      Delete